高级检索

特高压输电线路工程岩石锚杆基础优化方法研究

Research on Optimization Method for Rock Bolt Foundation in UHV Transmission Line Project

  • 摘要: 为满足山区特高压线路岩质地基建设需求,提升岩石锚杆基础安全、经济与环保性能,本文结合工程与规范,分析坡度、覆盖层、承台及锚杆布置等参数影响,开展多方案优化对比。结果表明:坡度35°时覆盖层≤1.5m,10°时≤3.5m;锚杆间距0.7m、承台方形布设、合理立柱偏心可实现受力与造价最优;锚杆中部抽空增效差、易产生应力集中,不推荐采用。该优化方案能缩减开挖与建材用量,保障基础承载力,可为同类工程设计施工提供参考。

     

    Abstract: To meet the construction needs of rock foundation for ultra-high voltage (UHV) lines in mountainous areas and enhance the safety, economy, and environmental performance of rock bolt foundations, this paper combines engineering practices and specifications to analyze the impact of parameters such as slope, overburden, bearing platform, and bolt arrangement, and conducts multi-scheme optimization and comparison. The results show that the overburden should be ≤1.5m when the slope is 35°, and ≤3.5m when the slope is 10°; optimal force distribution and cost can be achieved with bolt spacing of 0.7m, square arrangement of the bearing platform, and reasonable column eccentricity; the middle part of the bolt is not recommended due to poor efficiency and potential stress concentration. This optimized scheme can reduce excavation and building material usage, ensure foundation bearing capacity, and provide reference for the design and construction of similar projects.

     

/

返回文章
返回