配电网应急发电车快速并网控制技术研究

Research on Rapid Grid Connection Control Technology for Emergency Power Generation Vehicles in Distribution Networks

  • 摘要: 为解决应急供电连接效率过低,缺乏监控等问题,提出一种配电网应急发电车快速并网控制技术。该方法通过磷酸铁锂储能系统、快速夹持装置和热成像监控组件的协同设计,实现约5 min内完成并网连接的目标。测试结果表明,相比传统铜鼻子连接方式效率提升达87%~90%,温度监测误差小于±1.8 ℃,预警响应时间约为2.3 s,证明了该技术的高效性和可靠性。

     

    Abstract: To address issues such as low efficiency in emergency power supply connections and lack of monitoring, a rapid grid-connection control technology for emergency power generation vehicles in distribution networks is proposed. This method achieves the goal of completing grid connection within approximately 5 minutes through the coordinated design of a lithium iron phosphate energy storage system, a rapid clamping device, and thermal imaging monitoring components. Test results show that compared to traditional copper nose connection methods, efficiency improves by 87%~90%, temperature monitoring error is less than ±1.8 ℃, and warning response time is about 2.3 seconds, demonstrating the high efficiency and reliability of this technology.

     

/

返回文章
返回