巢湖市长江供水工程取水泵站电气设计探讨

Discussion on Electrical Design of the Pumping Station in Chaohu City Yangtze River Water Supply Project

  • 摘要: 综合考虑设备布置及汛期防护要求,巢湖市长江供水工程取水泵站采用双沉井布置,电气设备间尺寸严重受限。为此,分析了主变压器、高压开关柜、变频器等设备的选型方案,并规划了泵站进线电缆入站方式,为今后沉井泵站的电气设计提供了参考。

     

    Abstract: Considering equipment layout and flood season protection requirements, a double-caisson configuration is adopted, resulting in severely constrained dimensions for the pumping station of the Chaohu City Yangtze River Water Supply Project. In response to these characteristics, this paper analysis the selection schemes for main transformers, high-voltage switchgear, frequency converters, and other critical equipment. It also outlines the cable routing plan for the pumping station, providing a reference for future electrical designs of caisson-based pumping stations.

     

/