浅谈北京地铁5号线750 V直流牵引系统改造的调试

A Brief Discussion on the Commissioning of the 750 V DC Traction System Renovation of Beijing Subway Line 5

  • 摘要: 北京地铁5号线750 V直流牵引系统改造工程调试需夜间天窗点进行,每个天窗点施工时间只有2~3 h,调试项目多、影响范围大,充分利用天窗点时间对于改造工程尤为重要。通过对调试项目的梳理、排序和对调试方法的研究、总结,可以达到提高施工效率、确保地铁运营安全的目的,为以后的改造项目调试工作提供参考依据。

     

    Abstract: The commissioning of the 750 V DC traction system renovation project of Beijing Subway Line 5 needs to be carried out during the window, and the construction time for each window is only 2~3 hours. Due to the large number of commissioning items and the wide range of impact, it is particularly to make full use of the window time for the renovation project. By sorting out, sorting and summarizing the commissioning items and researching and summarizing the commissioning methods, the efficiency can be improved, the safety of subway operation can be ensured, and the commissioning work of future renovation projects can be provided with reference basis.

     

/